I am mentioning hereunder some merits of construction of
precast panel instead of cast in situ Retaining Wall.
A)COST: To construct RE Wall is much more cost
effective than cast in situ retaining wall. It was analyzed and found that 20
-25% cost we can save if we construct RE Wall instead of retaining wall.
B) TIME: Time has a great essence to any
contract. Lot of time can be saved if we construct facia panel,
synchronies program also possible if we plan to construct RE Wall. Below we
mention some practical aspect which shows how RE Wall construction is time
effective in comparison to retaining wall.
Ø In
RE Wall construction we can perform 2 activity simultaneously in a particular
time frame of time casting and fixing
the RE Panel and earth work but in retaining wall we can perform single work in
a time frame ,either casting of wall or earth work.
Ø In RE Wall construction there are no idle
construction phases. In Retaining wall construction there are 7 -14 days idle construction phase. Until
or unless cast in situ wall do not achieve the required strength we cannot able to perform the next
phase of work i.e. compaction of earth layer upto the RE WALL level.
Ø After deshuttering the retaining wall it shall
generally take minimum 4 -5 days for reuse shuttering and reinforcement for the next lift. In case
of facia panel casting it generally takes 24 hrs to reuse the shuttering.
Ø Progress Retaining wall casting depends on
availability of front at site, Facial panel casting-
progress is totally independent of front at
site.
Ø In case of urgency steam curing procedure can
be adopted in facia panel casting, but in RE Wall casting curing can be perform only using the
conventional method which takes minimum 14 days Over all it was observed
80% time can be saved if we construct RE WALL instead of retaining wall.
Ø AESTHETIC LOOK: RE Wall have a good and
variety of aesthetic look in comparison of retaining wall.
Ø QUALITY: Degree of quality control is
much higher in Precast Panel over cast in situ retaining wall.
Ø All and above Precast panel constructions are
accepted as good and variant solution to cast in situ.
STANDARD OR FULL-HEIGHT ‘’AN’’
PANELS OF SIZE 1.6M X 2.0M (WHERE 1.4 IS THE NOMINAL HEIGHT AND OTHER 2.0M – IS
THE C/C DISTANCE BETWEEN CENTER LINE AXIS OF THE AXIS OF THE PANEL SHOULDER)
ARE USED FOR THE MAJORITY OF THE WALL EACH PANEL IS REFERRED BY A LETTER WHICH
INDICATES THE TYPE OF PANEL AND A
NUMBERS, WHICH INDICATES THE NUMBER AND TYPE OF CONNECTOR AND ALSO THE TYPE OF
POLYMERIC STRIP ATTACHEMENT WITH A PARTICULAR PANEL.
Ø SETTING
UP OF CASTING YARD
Ø THE FOLLOWING FACILITIES SHALL BE SETUP IN
ORDER TO IMPLIMENT THE CASTING OF THE
PANELS IN MOST EFFICIENT WAY, AS WELL AS TO
PROVIDE THE BEST POSSIBLE QUALITY OF
WORK:-
Ø CASTING
AREA
Ø CASTING
AREA SHOULD NOT BE LOCATED IN AREA WHICH WILL MAKE BASIN OR LOW LANDS OF A PLOT
WHICH COULD GIVE RISE TO POUNDING OF WATER IN RAINY SEASON.
Ø IN
CASTING AREA PRECAUTION TO BE TAKEN UPTO PREVENT CASTED UNITS GETTING SPOLDING FROM
AFFECTS OF RAIN, SUNLIGHT ETC.
Ø A
CONCRETE, BRICK OR SIMILAR HARD FLOOR ASSURES THAT THE BASE PLATES OF THE MOULDS
ARE HORIZONTAL AND PROVIDES GOOD CONDITIONS OF WORK. SUPPORT PEDESTAL BEAM
MINIMUM 35CM WIDE SHALL SUPPORT THE BASE PLATE OF THE MOULDS. THEIR PURPOSE IS TO
PROVENT THE MOULDS FROM UNDESIRABLE DEFORMATION. AS WELL AS TO PROVIDE BETTER CONDITIONS
OF WORK.
FIXING OF MOULDS
TO FIX THE
SHUTTERS TO THE BASE PLATE. THE FOLLOWING PROCEDURE MUST BE FOLLOWED:-
Ø PLACE
THE TOP, BOTTOM AND SIDE SHUTTER ON THE TABLE. WITHOUT FIXING THEM YET.
Ø PLACE
THE CORNER SHUTTERS.
Ø FIX
THE SHUTTER TO THE BASE PLATE.
Ø FIX
THE SHUTTER BETWEEN THEM.
Ø IF
THE CUT SHUTTER IS USED. ASSURE THAT ITS POSSITION IS CORRECT.
Ø CASTING
Ø PREPARATION
:-
Ø PRIOR TO CASTING, THE BASE AND SIDES ARE
CLEANED SO THAT THERE IS NO DUST, CONCRETE WASTE ON THE BASE, BUFFER TO BASE
PLATES WILL BE DONE AS AND WHEN REQUIRED.
Ø MOULDS
ARE OILED WITH APPROVED QUALITY OF FORMWORK OIL AND EXCESS OIL IS TO BE REMOVED.
PLACING OF THE PANEL
ACCESSORIES
Ø TO
LIFTING ANCHORS WITH THEIR RUBBER RINGS ARE PLACED. THESE RUBBER RING CAN BE USED SEVERAL TIMES AND
THEREFORE SHALL BE COLLECTED BEFORE REMOVING THE PANEL FROM THE TABLE.
Ø FIX
THE OMEGA SELEEVE OF REQUIRED NUMBERS AS SHOWN IN THE PANEL DRAWINGS.
Ø REINFORCEMENT
AS PER THE PANEL DRAWINGS IS PLACED.
Ø POURING
THE CONCRETE
Ø THE
CONCRETE IS POURED IN EACH UNIT WITH A MINIMUM INTERRUPTION.
Ø A
NEEDLE VIBRATOR TO BE USED TO COMPACT THE CONCRETE.
Ø IT
MAY BE SUPPLEMENT THIS ACTION BY HAND TAMPING (MALLET) IN THE CORNERS.
Ø IT
IS IMPERATIVE TO MAINTAIN SLUMP OF THE CONCRETE BETWEEN 35 TO 45MM, DEPENDING UPON PREVAILING TEMPERATURE, THE
CONCRETE SUPPLYING AGENCY SHOULD TAKE CARE OF THE WEATHER AFFECTS TO ENSURE
CONSISTENCY OF SLUMP AT THE AMBIENT TEMPERATURES.
Ø THE
CONCRETE POURED IN 2-3 STAGES, EACH STAGE SHALL BE SPREADED USING
SPADE/FORK THEN VIBRATED BY NEEDLE
VIBRATORS.
Ø CURING
:-
Ø THE
WATER CURING SHALL START AS SOON AS THE CONCRETE STARTS TO DRY.
Ø A
CURING COMPOUND IF NECESSACRY MAY BE SPRAYED OR COVERED WITH DARK TARPULIN JUST
AFTER CASTING IN CASE OF VERY HOT TEMPERATURE.
Ø PANEL
MAY KEEP COVERED IN A HESIAN CLOTH PRIOR TO HANDLE THEM.
Ø PANELS
STACKED IN CURING STACKS MAY BE CURED BY SPRINKLERS PLACED AT A
Ø DISTANCE AND IN NUMBERS TO GIVE PROPER
COVERAGE TO THE UNITS TO BE CURED.
Ø SPRINKLING
CURING MAY BE FURTHER SUPPLEMENTARY BY MANUAL PIPE CURING WITH A SPECIAL ATTENTION TO AREAS WHICH ARE BEYOND OF
PRINKLERS SPRITZ.
Ø THE
PANELS SHALL STAY ON THE CURING AREA FOR 14 DAYS. PLACE NOT MORE THAN 5 (FIVE)
PANELS IN A STACK AND WOODEN BLOCKS TO BE USED AS SEPARATOR BLOCKS BETWEEN
STACKED.
Ø HANDLING
OF FACIA PANELS
Ø DE-MOLDING
Ø SIDE
SHUTTER WILL BE REMOVED AFTER 6/7 HOURS (MAY BE EXTENDED DURING WINTER CONDITIONS) AND THE PANELS WILL BE LIFTED
FROM THE BASE PLATE AFTER 20 HOURS OR
ATTAINING OF CUBE STRENGTH OF MINIMUM 10 MPA.
Ø REMOVAL
OF THE PANEL FROM THE BASE PLATE:-
Ø THE PANEL SHALL BE LIFTED BY MEAN OF A FOUR
POINTS SLING USING AN PPROPRIATE CAPACITY
OVERHEAD GANTRY CRANE OR FORKLIFT.
Ø IT IS TO BE NOTED THAT THE PANELS SHALL BE
LIFTED HORIZANTALLY ONLY WITH OMEGA SLEEVE AT FOUR CORNER TO AVOID ANY POSSIBLE
DAMAGE TO OMEGA SLEEVE DURING LIFTING AND RE-HANDLING PROCESS.
Ø JERKING AT THE TIME OF LIFTING AND SHIFTING
AT THIS STAGE SHALL BE AVOIDED.
Ø STACKING
OF FACIA PANELS
Ø STACKING
IN THE CURING AREA :-
Ø THE
STACKS OF PANELS SHALL BE PLACED ON A HORIZONTAL CONCRETE SURFACE.
Ø THE SURFACE SHALL HAVE BEEN PREVIOUSLY
COMPACTED.
Ø THE
MAXIMUM HEIGHT ALOOWED IS 5 (FIVE) PANELS IN ONE STACK.
Ø PANELS
SHALL BE STORED IN A HORIZONTAL POSITION WITH 10CM SPACER CUBES BETWEEN THEM IN
ORDER TO PREVENT THE CONNECTOR FROM BEING BENT OR DAMAGE.
Ø IT
IS DESIRABLE THAT SOME PLASTIC/RUBBER PADS SHALL BE FIXED ON THE TOP WOODEN BLOCKS TO PREVENT THE SPOTS ON THE FACE OF THE
PANELS (OPTIONAL).
STACKING IN THE YARDS :-
Ø THE
STACKS OF PANELS MUST BE PLACED ON A HORIZONTAL COMPACTED SURFACE.
Ø THE
USE OF RUBBER/PLASTIC PADS IS RECOMMENDED IF THERE IS ANY RISK OF RAIN DURING
THE STORAGE PERIOD, WHICH IS THE MOST PROBABLE CASE (OPTIONAL IF VISIBLE MARKS
ARE SEEN). THE PANELS CAN BE STORED IN STACKS UP TO 5 NOS.
TRANSPORTAION OF FACIA PANELS
Ø THE PANELS SHALL BE TRANSPORTED SO AS TO
PREVENT THE TOPPLING, AS WELL AS TO PREVENT UNDESIRABLE CONSTRAINTS IN THE
PANELS, STACKS OF PANELS SHALL NOT HAVE MORE THAN 5 (FIVE) UNITS DURING
TRANSPORTAION.
Ø SEPARATING EACH OTHER BY SUITABLE PADDING TO
PREVENT THR BREAKAGE/TRANSIT DAMAGES.
Ø PRIOR
TO THEIR ERECTION, THE PANELS SHALL BE STORED ON SITE IN THE SAME CONDITIONS AS
ON THE PRE-CASTING YARD STACKING AREA.
Ø REINFORCED
EARTH WALL SYSTEM-CONSTRUCTION METHODOLOGY
Ø THE WALL SYSTEM CONSIST OF ORIGINAL GROUND,
CONCRETE LEVELLING PAD DRAINAGE ARRANGEMENT CATERING TO CONSTRUCTION AND
SEVICE CONDITIONS, TERRATEE DISCRETE WALL FACING PANELS. DRAINAGE SYSTEM,
POLYMERIC STRIP, ACCESSORIES AND FITINGS, SELECTED BACKFIL AND TRAFFIC LOADS
AND SURCHARGE. ALL OF THESE ITEMS HAVE AN EFFECT ON THE PERFORMANCE OF THE RE
WALL AND ARE TAKEN INTO ACCOUNT IN THE DESIGN ANALYSIS. A CHANGE IN ANY OF
THESE ITEMS WOULD HAVE A DETRIMENTAL EFFECT ON THE WALL.
Ø SITE
PREPARATION
Ø FOR THE LENGTH OF THE RE WALL SECTION TO BE
BUILT. EXCAVATE THE SIRE TO THE DEPTH, GRADE AND WIDTH SPECIFIED IN NECESSARY,
AS PER SECTION 201 AND 305 OF MORHT SPECIFICATION.
Ø LEVEL AND COMPACT THE FOUNDATION IN ACCORDANCE
WITH THE PROJECT SPECIFICATIONS/CONSTRUCTION DRAWING.
Ø ESTABLISH FORMWORK FOR LEVELLING PAD FORMWORK
SHALL CONSIST OF TWO NUMBER OF ISMC 150
CHANNELS, IN-PLACE ARRANGEMENT TO MARCH THE SECTION AND ALIGNMENT OF LEVELLING
PAD.
Ø MARK THE PAD ALIGNMENT ON THE COMPACTED
FOUNDATION LAYER CONSIDERING THE ADDITIONAL WIDTH(C/C DISTANCE BETWEEN TWO
PADS) WILL VARYDEPENDING ON HEIGHT OF WALL AT THAT LOCATION.
Ø POUR THE CONCRETE LEVELLING PAD, THE PAD
SHOULD BE CURED FOR 3 DAYS PRIOR TO USE, OR LONGER IF REQUIRED THE CONCRETE
FINISH MUST BE SMOOTH AND FLAT AND MUST NOT VARY FROM THE DESIGN ELEVATION MORE THAN 3mm.
Ø INSERT
16MM DIAMETER PEGS IN THE CONCRETE, CARE TO BE TAKEN WHILE DRIVING THE PEGS
THAT FINISHED CONCRETE SURFACE SHOULD NOT GET AFFECTED, IF PLANS CALL FOR
THE WALL TO HAVE A STEP UP IN ELECATION,
POUR THE HIGHER LEVELLING PAD SO THAT ITS
SURFACE IS 0.800M ABOVE THAT OF LOWER PAD. LEAVE A 350mm GAP BETWEEN THE
NEW PAD.
Ø ERECTION
OF PANELS
Ø SNAP
A CONTROL LINE ON THE SURFACE OF THE LEVELLING PAD USING LIME OR MARINE BULE.
ANCILLARY REFERENCE POINT SHOULD BE MARKED ALONG WITH CONTROL LINE. INDICATING
THE POSITION OF CURVES, CORNERS, SLIP JOINTS ETC. IT IS DESIRABLE TO MARK
CONTROL POINTS ON THE CURVE AT CLOSER INTERVAL
Ø PLACE
THE FIRST B(n) (HALF) PANEL 1 ON THE LEVELLING PAD. ALIGN THE FACE OF THE PANEL
ALONG THE CONTROL LINE ON LEVELLING PAD,
AND USING HARDWOOD WEDGES, SET BATTER OF THE PANEL,
Ø PLACE
THE SECOND B(N) PANEL 2 ON LEVELLING PAD. ALIGN IT WITH THE CONTROL LINE, AND SET IT THE CORRECT DISTANCE FROM THE PANEL 1.
Ø PALCE
A(N) (FULL) PANEL 3 BETWEEN THE TWO HALF PANEL 1 AND 2, CENTER THE PANEL TO
ENSURE EQUAL VERTICAL JOINTS. WHEN PLACING PANELS, MATCH THE CENTER OF INDENT
ON SHOULDER OF ONE PANEL TO THE CORRESPONDING MARK IN THE ADJACENT PANEL, SET
THE PANEL’S BATTER AS BEFORE, CLAMPS THE PANEL TO PANELS 1 AND 2 TIGHTEN
CLAMPS SUFFICENTLY TO HOLD THE PANEL IN
POSITION WITHOUT MOVEMENT.
Ø WHEN
THE PANELS HAVE BEEN SET RE-CHECK WALL ALIGNMENT BY SIGHTING ALONG THE WALL FACE. IF NECESSARY, ADJUST PANELS TO
OBTAIN A TRUE LINE. CHECK THE SET VATTER AND BEGIN BRACING THE INITIAL COURSE OF
PANELS. USE TIMBER BRACE FOR EACH FULL PANEL. COMPACTION SHALL NOT BE LESS THAN
95% OF THE MDD BEYOND 1.5M FROM THE REAR FACE OF THE PANELS. HOWEVER, IN THE
ZONE WITHIN 1.5M FROM REAR FACE OF THE PANEL, COMPACTION SHOULD NOT BE LESSER
THAN 90% OF THE MDD.
Ø DURING
CONSTRUCTION CHECK THE OVERALL SLOPE OF THE STRUCTURE AT EACH COURSE USING A
TEMPLATE.
Ø PLACE
REINFORCING POLYMERIC STRUP ON THE COMPACTED BACKFILL POSITION IT
PERPENDICULARLY TO PANELS. FOLD THE POLYMERIC STRIP AT THE PANEL FACE AND PASS
THE FOLDED PORTION THROUGH THE OMEGA
SLEEVE. PULL THE POLYMERIC STRIP IN POSITION, THE POLYMERIC STRUP MUST BE PLACE AT 5%DOWN SLOPE.
Ø FOR
ALL HORIZONTAL JOINTS OF PANELS 200MM WIDE FEOREXTILE SHALL BE USED AND ALL
VERTICAL JOINTS OF PANELS 400MM WIDE GEOTEXTILE SHALL BE USED.
Ø BACKFILLING
Ø THE CONTRACTIBILTY AND PERFORMANCE OF A
REINFORCED EARTH STRUCTURE ARE DIRECTLY RELATED TO THE BACKFILL QUALITY AND IN
THE MANNER IN WHICH IT IS PLACED.
Ø SPREAD THE BACKFILL BY PUSHING THE PILE
PARALLEL TO THE PANELS AND WIDROWING IT TOWARD THE PANELS AND TOWARDS FREE ENDS
OF THE POLYMERIC STRIPS.
Ø IF POLYMERIC STRIP LENGTHS IS LONG, A SECOND
LOAD MAY BE REQUIRED TO BACKFILL TO THE END OF THE STRIPS, IF SO, DUMP AND
SPREAD THIS LOAD ONLY AFTER SPREADING THE FIRST.
Ø THE SELECTED BACKFILL SHALL BE PLACED AND
COMPACTED TO THE FIRST ROW OF CONNECTIONS TO THE DENSITY AS SPECIFIED THE
COMPACTED FILL LEVEL SHOULD BE AT OR SLIGHTLY HIFHER THAN THE PANEL CONNECTIONS
LEVERL. ON THE INTIAL ROW OF PANELS (AND ONLY THE INTIAL ROW OF PANELS) THE
BACK FILL IS NOT PLACED AGAINST THE
PANEL UNTIL THE FIRST ROW OF PLYMERIC STRIP HAVE BEEN CONNECTED & THEN FILL
IS PLACED ON THE POLYMERIC STRIP, THIS TO KEEP THE BOTTOM OF THE PANELS FROM
‘’KICKING OUT’’, FROM THAT POINT, THE BACKFILL IS BROUGHT UP UNIFOTMLY FROM THE BACK OF THE PANELS TO THE END OF
POLYMERIC STRIP.
Ø COMPACTION
Ø BEFORE
COMPACTION IS STARTED PLACE PROPS SO AS NOT TO ALLOW ANY OUTWARD MOVEMENT OF
PANELS FOR 2 LAYER, WEDGES MUST ALSO BE USED TO PREVENT SUCH MOVEMENTS.
Ø COMPACTION
EQUIPMENT USED WITHIN 1.5M OF THE WALL SHOULD BE A WORK BEHING ROLLER OR PLATE
ROLLER WEIGHING NOT LESS THAT 1 MT CAPACITY ENSURING DENSIT OF MIN. 90% OF
MIXIMUM PROCTOR DRY DENSITY.
Ø BEYOND
1.5M FROM THE WALL FACING PANELS A ROLLER UPTO 8 TONNES VIBRAORY ROLLER WITH 8
TO 10 PASSES MAY BE USED SUBJECT TO SARISFACTORY PERFORMANCE.
Ø BACKFILL
COMPACTION SHALL BE PERFORMED IN SUCH A WAY THAT THE COMPACTOR SHALL MOVE IN A DIRECTION PARALLEL TO THE WALL
FACING PANELS AND WORK TOWARD THE END OF THE SOIL REINFORCEMENT AWAY FROM THE
WALL FACING. TO ACHIEVE MIN. 95% OF
MAXIMUM MODIFIED, PROCTOR DRY DENSITY.
Ø THE
COMPACTION EQUIPMENT ROLLS PARALLEL TO THE WALL FACING, COMPACTION STARTS AT
LEAST 1.5M FROM THE WALL AND WORKS TOWARDS THE END OF THE REINFORCEMENT.
Ø REPEAT
ABOVE STEP UNTIL THE TOP OF THE WALL IS REACHED. AS SOON A PRACTICAL THE FRONT
OF THE WALL SHOULD BE BACKFILLED . THIS SHOULD OCCUR PRIOR TO REACHING THE TOP
OF THE WALL.
A dedication of thankfulness is at the same time For Sharing! by then during a general sense Visit
ReplyDeleteSmall Retaining Wall Construction
Iron Clipper - 2 2 3 3 3 4 - Titsanium Arts
ReplyDeleteIron Clipper is a 2-3 3-4" 3-4" iron rod with 1 gauge edge. Made in Solingen, Germany, Iron Clipper is a 2-3-4" 3-4" rod with 1 gauge edge. Made in Solingen, Germany, Iron Clipper is a 2-3-4" 3-4" Material: Solingen, Material: MetalReelsDimensions: 9 x 7 x 3 x 0 titanium rod in femur complications inches; 9 ridge titanium wallet cm; 8.5 inchesWeight: 8.5 oz titanium bikes Rating: 5 · 2 reviews 메이플 캐릭터 슬롯 · $19.95 · titanium wire In stock
The retaining wall cost depends on the size and type of wall you choose. The average cost of a retaining wall is between $6 and $20 per square foot. Costs can vary depending on the type of materials used, the complexity of the project, and other factors.
ReplyDeleteThe Craft Beer App should have an extensive database of craft beers, including information on breweries, beer styles, ABV (alcohol by volume), IBU (International Bitterness Units), and tasting notes.
ReplyDelete